Construction Update: Aberdeen Student Property

Jan 22, 2017
Tags: Aberdeen

*this is an update to an article that was first published 12th March 2014

Aberdeen Student Property: construction timeline

Detailed construction updates and images of Aberdeen Student Property, our purpose built property in Scotland.

This new build development consists of 30 en-suite purpose built bedrooms spread across four levels.

Each 6-bed apartment has its own kitchen and communal space, making it an attractive option for students at Aberdeen’s three universities.

Due to the prime city centre location, proximity to the universities and college as well as local amenities, this property will experience sustained high demand. This ensures it will remain a sought-after asset for future investors.

 

Construction timeline

8th June 2015

  • Kitchens fitted
  • 2nd fix electrical, joinery and plumbing completed
  • Flooring completed
  • Paintwork completed
  • En-suites fitted

27th June 2014

  • The build is at roof height level

24th June 2014

  • Construction of second floor

12th June 2014

  • Construction of first floor

6th June 2014

  • Timber frame arrives and construction of ground floor

23rd May 2014

  • Concrete floor being laid

16th May 2014

  • The foundations are completed
  • Commencing with block work and lift shaft prior to the timber frame’s arrival
  • Timber frame due to arrive on 30 May
  • Roof height expected 13 June

8th May 2014

  • The concrete is being poured
  • The timber frame is due to arrive on site

29th April 2014

  • The metal cage supports for the foundations are in

12th March 2014

  • Piling for foundations has been completed
  • Concrete foundations are being put in
  • Timber frame due on site in three weeks
  • The site has been cleared – an old garage and shed were taken down and a boundary wall removed
  • Piling for the foundations is due to commence next week

 