Construction Update: Jubilee Court Student Property

Jubilee Court construction student property
Jul 8, 2016

*this is an update to an article that was first published 27th June 2015

Jubilee Court: Construction timeline

Detailed construction updates and images of Jubilee Court, our new build purpose built student accommodation in Preston.

Jubilee Court delivery timeline

This property contains 241 purpose-built student units, all with en-suites, Wi-Fi and quality furnishings and fittings throughout. It is being built by our experienced student developer, holder of an NHBC award for build quality.

Residents will have access to a wide range of facilities that places the property at the top of Preston’s student accommodation sector. These include a gym, games room and advanced security systems.

 

Construction timeline

7 June 2016

Jubilee Court Construction 7 June 2016

  • Phase I complete internally and ready for sign-off
  • Scaffolding to be dropped by end June
  • Phase II will be ready for sign-off end July
  • Waiting for main electrics to be connected, to start final testing

3 March 2016

 Jubilee Court Construction 3 March 2016

  • Roof 85% complete
  • (Phase 1) Windows, first fix plumbing and electrics complete
  • (Phase 1) Boarding progressing well

25 January 2016

Jubilee Court Construction 25 January 2016

  • Windows 50% complete
  • Roof 50% complete
  • First fix electrics 25% complete
  • First fix plumbing 25% complete
  • Boarding 25% complete
  • First fix joinery 15% complete
  • Plastering 15% complete

30 November 2015

Jubilee Court Construction 30 November 2015

  • Timber frame reached sixth and final level on first building
  • Started first fix electrics and plumbing
  • Started installing windows
  • Started work to roof structure

14 October 2015

Jubilee Court Construction 14 October 2015

  • Started to form internal walls on the ground floor
  • Scaffolding in place up to third floor
  • Timber frame being hoisted into place

29 September 2015

Jubilee Court Construction 29 September 2015

  • Timber frame arrives on site

8 September 2015

Jubilee Court Construction 8 September 2015

  • Pile foundations 100% complete
  • Concrete ring beam 80% complete
  • Concrete floor will be poured next
  • Timber frame due to arrive in October

12 August 2015

Jubilee Court Construction 12 August 2015

  • 250 piles driven and piling complete
  • Foundations 100% complete

27 July 2015

Jubilee Court Construction 27 July 2015

  • Piliing has commenced
  • 40/240 piles are in position

9 July 2015

Jubilee Court Construction 9 July 2015

  • Site being levelled in preparation for puling
  • Timber frame being manufactured off-site
  • Site being cleared of vegetation

 