Construction Update: Westbeach Luxury Serviced Apartments & Spa

Westbeach Devon construction
May 28, 2017

*this is an update to an article that was first published 31st December 2013

Westbeach, Devon: construction timeline

Detailed construction updates and images of Westbeach, Devon – our new build property investment in Westward Ho!

Westbeach construction timeline

These beachside serviced apartments will be well equipped with a private kitchen and large open plan living space and hi-spec features like flat screen TVs, Wi-Fi and underfloor heating.

Westbeach is partly operational and is already TripAdvisor’s top ranked accommodation option in Westward Ho!. It also holds a four-star accreditation from VisitEngland, the national tourism board.

Facilities under construction include a luxury spa and Westward Ho!’s only indoor swimming pool. The property will also have a central complex with a rooftop swimming pool and sunken bar.

Westbeach, Devon

 

Construction timeline

28 May 2017

  • Steel frame for central core going up

6 April 2017

  • Concrete pour for Phase 4 complete
  • Steel frame starting to be built from mid-May. Central core steel frame will be built first
  • This will be followed by simultaneous installations for Phase 3 and 5, and then Phase 4 and 6

5 April 2017

  • Cages in place for concrete pour for Phase 4’s foundations

1 February 2017

  • Roadway retaining structure complete
  • Steel frame in factory being made, ready for delivery from March 2017
  • Once cast, upper floor ground beams will be set and foundation works will be complete
  • Engineering bricks in place, ready to start to form substructure on phases 3 and 5
  • Total cost for ground works and civil engineering around £2m of which work for £1.7m has been completed
  • All storm drains are being put into the site currently – to be finished prior to the steel frame arriving on site in March
  • Two teams will be able to work on parts of the steel frame concurrently. Core to be worked on first, then phases 3 and 5, then the second team can begin work on phases 4 and 6
  • Expected date of completion of build per phase is below, with phases 3 and 5 expected before Easter 2018. The remaining phases are likely to open together before the summer season gets fully underway in June 2018
  • Expected completion dates are: Phase 3 – February 2018; Phase 4 – March 2018; Phase 5 – April 2018; Phase 6 – May 2018

30 November 2016

  • Phase 3 retaining walls almost complete, to enable roads around to be constructed
  • Phase 4 ground beams under way

2 November 2016

  • Ground beams and concrete pads for phase 3, 5, 6 and central core complete

7 December 2015

Westbeach Construction 7 December 2015

  • Phase II completed
  • All building work completed; buildings signed
  • Ready to accept guests at Easter
  • Furniture to be fitted ahead of the March/Spring season
  • Phase III: Foundations complete
  • Phase IV: Foundations to be completed end of January
  • Phases IV & VI: Foundations to be completed late spring
  • Roof on expected August 2016

5 August 2015

Westbeach Construction 5 Augustr 2015

  • New car park and access road complete
  • Site around block 1 and 2 opened
  • Interconnecting road surfacing and paving being completed
  • Final fix items ex. Smoke detectors to be installed
  • Snagging list and exting (ex. Electrics) to be completed
  • Builders cleans carried out on 50% of the block
  • Carpets and furniture to be installed
  • Building Control arranging final inspections for sign off

1 July 2015

Westbeach Construction 1 July 2015

  • Infrastructure works and foundations are progressing well on Phase III
  • Majority of ground work almost complete
  • Designs being finalized on remaining phases, with foundation works due to start in two weeks
  • Phase II apartments nearing completion
  • Builders clean scheduled for third week in July
  • Carpets and furnishings to follow
  • All hard landscaping and parking around block one and connecting top block two is now almost complete
  • Operational by end of July

13 February 2015

Westbeach Construction 13 February 2015

  • Installation of kitchens, fixtures and fittings, decorations and completion of tiling due to start shortly

8 August 2014

Westbeach Devon 8 August 2014

  • First fix electrical, plumbing and heating progressing well
  • Outer masonry skin, lift shaft and balcony sections are underway

2 July 2014

Westbeach Construction 2 July 2014

  • Walls are being plaster boarded

24 June 2014

Westbeach Construction 24 June 2014

  • Insulation has been installed in the walls
  • Electrical first fix wiring complete
  • Ceillings have been plaster boarded

15 May 2014

Westbeach Construction 15 May 2014

  • The roof is on

9 April 2014

Westbeach Construction 9 April 2014

  • The superstructure completion is still on target for end April. This is where the build reaches the roof wall plate level, ready for the roof to go on.
  • Scaffolding being erected
  • Timber frame being manufactured at factory

31 March 2014

Westbeach Construction 31 March 2014

  • Substructure work is progressing well and set to be completed by 4th April. Scaffolding will be erected this week and the superstructure is set to commence on 7th April

12 March 2014

Wesrtbeach Construction 12 March 2014

  • Construction is on schedule despite the bad weather that has affected other parts of Devon.
  • Work on the superstructure will commence on the 24th March

12 February 2014

Westbeach Construction 12 February 2014

  • Work on the foundations has started

31 December 2013

  • Site cleared

 